Commercial · 2024

Office Refurbishment

Two-floor office refurbishment delivered without business downtime — staff relocated floor-by-floor as works progressed.

Programme
10 weeks
Floor area
4,200 sq ft
Phases
2
Refurbished open-plan floor

Refurbished open-plan floor

1 / 2

Location

Meru

Year

2024

Duration

10 weeks

Size

4,200 sq ft

Client

Professional services firm

Type

Two-floor office refurbishment

The brief

The client could not vacate. Our remit was a phased refurbishment that kept one floor fully operational at all times while the other was under works.

Scope of works

  • Phased strip-out and rebuild, one floor at a time
  • New partitioned offices and meeting rooms
  • Acoustic ceiling system with integrated lighting
  • Carpet tiles, painted walls, joinery to brand standard
  • Power, data and HVAC adjustments to new layout

On site

Challenges & how we handled them

Live-work site management

Noise, dust and movement controls were planned per phase. Heavy works were scheduled outside core hours; daily site walks were carried out with the client lead.

Outcomes

  • Zero business downtime across 10 weeks of works
  • Client retained all client-facing meeting capacity throughout