Retail interior fit-out delivered inside a 6-week shutdown window, including bespoke joinery, lighting and finishes.

Programme
6 weeks
Floor area
1,400 sq ft
Shifts
2 (final fortnight)
Completed shopfront

Completed shopfront

1 / 2

Location

Meru CBD

Year

2023

Duration

6 weeks

Size

1,400 sq ft

Client

Retail brand

Type

Retail interior fit-out

The brief

The brand had a hard reopening date tied to a national campaign. Programme certainty was the single most important constraint — finishes were second.

Scope of works

  • Strip-out of existing finishes and partitions
  • New stud partitions with acoustic insulation
  • Bespoke display joinery in painted MDF and hardwood trim
  • Track lighting, power and data to retail layout
  • Vinyl flooring, painted walls, signage substrate

On site

Challenges & how we handled them

Shutdown window

Six weeks meant finishes had to overlap with second-fix MEP. We ran two shifts in weeks 4 and 5 and pre-fabricated joinery off-site.

Outcomes

  • Reopened on the campaign launch date
  • Zero defects raised in the first 30 days post-opening