The brief
The brand had a hard reopening date tied to a national campaign. Programme certainty was the single most important constraint — finishes were second.
Scope of works
- Strip-out of existing finishes and partitions
- New stud partitions with acoustic insulation
- Bespoke display joinery in painted MDF and hardwood trim
- Track lighting, power and data to retail layout
- Vinyl flooring, painted walls, signage substrate
On site
Challenges & how we handled them
Shutdown window
Six weeks meant finishes had to overlap with second-fix MEP. We ran two shifts in weeks 4 and 5 and pre-fabricated joinery off-site.
Outcomes
- Reopened on the campaign launch date
- Zero defects raised in the first 30 days post-opening